In November 2016, Wake County voters approved a transit plan that named four bus rapid transit corridors for implementation by 2027. By the City of Raleigh's current schedule, late 2027 is when crews start work in the downtown core of the first one.
That gap matters if you're comparing Raleigh neighborhoods and keep seeing "future BRT" on corridor maps or in listing descriptions. All four lines are real City projects with published schedules. None of them carries riders yet. The earliest service target the City lists is 2028 to 2029, for the Southern line, and it depends on federal funding. New Bern Avenue, the only line under construction, is scheduled to finish in 2030. For a buyer, the useful question about a home near a planned station is where its line sits on that timeline. Is it in construction, final design or early study? Each stage means something different for the street you'd live on over the next several years.
Four lines, four stages
Here is where each corridor stands as the year ends, taken from the City's own project pages.
| Corridor | Route | Stage, November 2026 | Next dated milestone |
|---|---|---|---|
| New Bern Avenue | GoRaleigh Station downtown to New Hope Road and WakeMed, 5.1 miles | Under construction since early 2026 | Final construction package, including stations, to be advertised by end of 2026; completion in 2030 |
| Southern | Downtown Raleigh to Garner via South Wilmington Street and Fayetteville Road, about 5 miles | Final design | Federal risk review winter 2026; property acquisition 2027; construction target 2028, depending on federal funding |
| Western | Downtown Raleigh to downtown Cary via Western Boulevard, Cary Towne Boulevard, Maynard Road and Chatham Street, about 12 miles | 30% design nearing completion | Environmental review summer 2027; construction 2030; service 2032 |
| Northern | Toward Midtown/North Hills and Triangle Town Center | Route alignments adopted September 16, 2026 | Design procurement |
Only one of these lines has crews in the street. That makes New Bern Avenue the best guide to what the other three corridors will go through when their turn comes.
New Bern Avenue is the work itself through 2030
The New Bern Avenue project runs 5.1 miles. About 3.3 miles will have dedicated transit lanes between the downtown GoRaleigh Station and Sunnybrook Road, and the bus will share general traffic lanes from Sunnybrook out to New Hope Road. The City picked it to go first because a pedestrian project was already planned along part of the avenue and transit ridership on the corridor was high. In 2020 the City Council folded the two projects together so the corridor wouldn't go through construction twice in a row.
The groundbreaking ceremony was November 7, 2023, and construction started in early 2026. The City's posted timeline breaks the work into segments. Utility work between Poole Road and Person Street runs from spring 2026 into winter 2027. Clearing between Poole Road and Sunnybrook Road was scheduled for summer and fall 2026. Utility and multi-use path work around Morgan Street fills fall and winter 2026, and the core downtown area follows in late 2027. The City's construction map says a Morgan Street crew began replacing a waterline in September 2026, with curb, gutter, stormwater work and the multi-use path to follow.
You can see this on the street. Earlier this month the City scheduled two weekends of westbound closures on New Bern Avenue between Raleigh Boulevard and St. Augustine Drive, with traffic detoured via Raleigh Boulevard and Poole Road. GoRaleigh Route 15 still runs during construction. Its stops at Swain Street and Idlewild Avenue have been removed, and the East Morgan Street at South Person Street stop is temporarily closed, with riders directed to New Bern at East Street or Morgan at Wilmington.
ABC11 reported in August 2026 that businesses along the corridor were dealing with traffic backups and shifting customer patterns. Trees along the avenue had been taken down, and some business owners and homeowners had parts of their property acquired for the project. The same report also covered a new shop on the corridor, All Kinds, with North Carolina beer, wine and locally made goods, which was scheduled to open in August. Businesses are opening on New Bern Avenue while the lanes are still torn up.
The City's November 6 update says the third and final construction package, which covers building the BRT stations themselves, will be advertised by the end of this year. Until that package is awarded and built, the corridor will have lane work, utility work and path work, but no stations.
What's already standing along New Bern
Some of the housing along the corridor is already finished. Milner Commons, a 156-unit affordable community near King Charles Road built by the nonprofit DHIC, was complete and occupied as of WUNC's February 2026 report. The City's FY2027 adopted budget lists New Bern Crossing as a completed FY2026 project with 192 units.
The biggest open question on the avenue belongs to the City. It bought the 5.88-acre former DMV headquarters at 1100 New Bern Avenue in June 2024, and its October 2026 project update describes demolition prep and a market study for future development. What goes on that site is still to be decided, and that decision will shape the blocks nearest downtown as much as the bus lanes will.
So on New Bern you can judge the corridor by what has actually been built and what is under construction. On the other three lines, all you have is a schedule.
The other three lines are a different kind of wait
The Southern corridor will link downtown Raleigh, South Wilmington Street and Fayetteville Road, North South Station, and Rupert Road in Garner. It is in final design. The project schedule runs through a winter 2026 federal risk review and property acquisition in 2027. The City's Wake BRT FAQ sets a 2028 target to begin corridor and station construction and a 2028 to 2029 target for service, with the timing tied to federal funding and final design. If you're looking along South Wilmington Street or Fayetteville Road, construction could reach your street before the New Bern line is done, as long as those funding milestones hold.
The Western corridor matters to both Raleigh and Cary buyers. It runs about 12 miles from GoRaleigh Station to downtown Cary, using dedicated lanes in some places and mixed traffic in others. Its 30% designs are close to final, and public engagement restarts when they are done. The City expects to finish environmental review in summer 2027, start construction in 2030 and begin service in 2032. Because the route ends on Chatham Street, the line reaches the same downtown Cary blocks we covered in our piece on Chatham Street's new center of gravity. Someone buying near Western Boulevard or downtown Cary in 2026 could own the home for years before the first construction crew arrives.
The Northern corridor is the earliest of the four. The Raleigh City Council endorsed its study on May 19, 2026, and CAMPO adopted the route alignments toward Midtown/North Hills and Triangle Town Center on September 16, 2026. The City's October 29 update lists procurement of planning, engineering and design work as the next step. In North Raleigh today, the line is a chosen route without a design.
Reading a listing that mentions BRT
Once you know the stage, a vague selling point becomes something you can check. A few habits help when you're comparing homes along these corridors:
- Find the segment on the City's project page, not just the corridor. On New Bern, Morgan Street, Poole Road to Person Street and the downtown core each have different work windows.
- Check GoRaleigh's rider alerts for the stops closest to the home. Route 15 is still the transit you can actually use on New Bern, and several of its stops have moved during construction.
- On the Southern corridor, 2027 property acquisition and the 2028 construction target are the milestones to watch. On the Western corridor, it's the summer 2027 environmental review, with construction not expected until 2030.
- On the Northern corridor, look at the route itself. Street-level details come after design work that hasn't been contracted yet.
None of this makes a corridor home a better or worse choice. It just means the decision is about timing, and you're comparing what living near a line looks like in 2027 and 2028 with what it might look like in 2030 or 2032. Our Raleigh neighborhood page and Cary neighborhood page cover the areas these lines pass through.
If a home near one of these corridors is on your list, or you own one and want to know how the construction calendar fits your plans to sell, Hendren Realty Group can go through the segment schedule with you street by street. Reach out through our contact page and we'll help you match your move to where the line will be when you get there.